Present Status

Line I ( Shahdara – Rithala)

Line – I ( Shahdara – Rithala) was made operational for commercial services in three stages:

  1. Shahdara – Tis Hazari : with effect from 25th Dec, 2002.

  2. Tis Hazari – Inderlok : with effect from 4th Oct, 2003.

  3. Inderlok – Rithala : with effect from 1st April, 2004. With this Line I was completed.

Line II ( Vishwavidyalaya – Central Secretariat)

Line II (Vishwavidyalaya – Central Secretariat) was made operational for commercial services in two stages :
  1. Vishwavidyalaya – Kashmere Gate : with effect from 20th Dec, 2004.

  2. Kashmere Gate – Central Secretariat : with effect from 3rd July, 2005. With this Line II was completed.  

Line III ( Indraprastha - Barakhamba Road - Dwarka Sub City)

Barakhamba Road - Dwarka Section : was made operational for commercial services with effect from 31st December, 2005.

Extension of Line III

  1. Extension into Dwarka subcity : was made operational for commercial services with effect from 1st April, 2006.

  2. Barakhamba Road- Indraprastha Extension : was made operational for commercial services with effect from 11th November, 2006.

Rolling Stock

23 (21) trains for Line - I
13 (12) trains for Line - II
24 (27) trains for Line- III

Overall Progress

By (With the) opening of Line -3 (Barakhamba Road - Indraprastha Extension ) on 11th Nov. 2006, Phase -I has been successfully completed.
The current overall progress of Phase - II Project is 8.96% (16%).