Phase 1
Network | Project Cost
| Expected Ridership |
Present Status
| Training School | Delhi
Metro is a world class Metro | Consultancy Project
Present Status
Line
I ( Shahdara – Rithala)
Line – I ( Shahdara – Rithala) was made operational for commercial services in three stages:
-
Shahdara
– Tis Hazari : with effect from 25th Dec, 2002.
-
Tis
Hazari – Inderlok : with effect from 4th Oct, 2003.
-
Inderlok
– Rithala : with effect from 1st April, 2004. With this Line I was completed.
Line
II ( Vishwavidyalaya – Central Secretariat)
Line II (Vishwavidyalaya – Central Secretariat) was made operational for commercial services in two stages :
-
Vishwavidyalaya
– Kashmere Gate : with effect from 20th Dec, 2004.
-
Kashmere
Gate – Central Secretariat : with effect from 3rd July, 2005. With this Line II was completed.
Line
III ( Indraprastha - Barakhamba Road - Dwarka Sub City)
Barakhamba
Road - Dwarka Section : was made operational for commercial services with effect from 31st December, 2005.
Extension
of Line III
-
Extension
into Dwarka subcity : was made operational for commercial services with effect from 1st April, 2006.
-
Barakhamba
Road- Indraprastha Extension : was made operational for commercial services with effect from 11th November, 2006.
Rolling Stock
23 (21) trains for Line - I
13 (12) trains for Line - II
24 (27) trains for Line- III
Overall
Progress
By (With the) opening of Line -3 (Barakhamba Road - Indraprastha Extension ) on 11th Nov. 2006, Phase -I has been successfully completed.
The current overall progress of Phase - II Project is 8.96% (16%).
|